CRS setup the control network for the site in advance of the construction staking phase. The staking of the site consisted of approximately 30,000-linear feet of roadway, over 22,000-linear feet of V-shaped drainage ditches with seven (7) storage ponds, over 90,000-linear feet of conduit trenching, and 23 power station pad sites. The staking for the entire site was completed in six (6) weeks. During the construction phase, CRS supported the effort with minor re-staking trips along with as-built survey services.